Wednesday, October 20, 2010

Gold Stocks, Orezone's (TSX: ORE.TO) Bombore Gold Project Has Substantial Increase in Size and Grade

Gold Stocks, Orezone's (TSX: ORE.TO) Bombore Gold Project Has Substantial Increase in Size and Grade

OTTAWA, ONTARIO-- (http://www.investorideas.com/ gold and mining stocks blog) - Orezone Gold Corporation (TSX: ORE.TO) is pleased to announce that gold mineral resources at its 100% owned Bombore Gold Deposit located in Burkina Faso, West Africa have substantially increased to 60.9 million tonnes of indicated mineral resources at a grade of 0.81g/t for 1.6 million oz of gold plus 60.6 million tonnes of inferred mineral resources at a grade of 0.96g/t for 1.9 million oz. "Bombore is now the largest undeveloped gold deposit in Burkina Faso and it remains open at depth and along strike" said Ron Little President and CEO. "Orezone will immediately commence an aggressive infill and expansion drill program to further expand mineral resources in conjunction with completing a preliminary economic assessment."
The mineral resource update includes this year's 42,456m (619 holes) infill and expansion reverse circulation ("RC") drill program that was designed to upgrade and test the limits of the surface oxide resource. The program was successful and also served to increase the continuity and grade of the fresh rock resource below. This unexpected and material change to the total mineral resource warrants a change in the Company's approach to also consider developing the project as a carbon in leach ("CIL") operation. The deposit is still open on surface where more oxide material is targeted. However, the potential to significantly increase the fresh rock mineral resources at a grade of 1.0g/t or higher in the top 200m from surface is now an equally high priority. The Company's board of directors has approved a short term drilling budget of $2.5M to commence core drilling and to secure additional drilling equipment. As part of this budget, several kilometres of new surface targets will also receive RC drilling. Orezone intends to continue with its plan of completing a preliminary economic assessment of the project by the first quarter 2011. The assessment will now include both heap leach and CIL scenarios.
The mineral resources were estimated by the Company and audited by SRK Consulting (Canada) Inc. ("SRK") (Table 1). The mineral resources are constrained within 4.3km2 of conceptual optimized open pit shells (11km long and up to 1km wide) with an estimated stripping ratio of 2.2:1. Approximately 80% of the total resource occurs in the top 80m, but pit shells can reach a depth of 200m. Resources are totally open at depth and 90% of the drilling to date is within 60m of the surface. The pit shells are based on a US$1,025 gold price, relevant cost estimates for mining, processing, G&A, and detailed metallurgical results (reported December 2009) to estimate recoveries for a CIL plant scenario. The mineral resource model is based on a total of 120,605m of RC and core drilling data compiled up to August 2010. The project is situated beside the main highway just 85km east of the capital city of Ouagadougou. Infrastructure in the flat lying area is excellent with a low population density and access to power and water.
"With 35,000 ounces of gold per vertical metre in the top 60m of the deposit, there remains excellent potential to significantly increase resources at depth as we extend the definition drilling to a depth of 120m," said Pascal Marquis, V.P. Exploration for Orezone. "We have still not exhausted the surface oxide targets or the potential of lateral extensions to our current open pit shells which will also receive more drilling."
Table 1
2010 Audited Mineral Resource Statement(i) for the Bombore deposit, Burkina Faso, West Africa, SRK Consulting, October 15, 2010, CIL Processing Scenario

--------------------------------------------------------------------------
                   Indicated Mineral Resource     Inferred Mineral Resource
 --------------------------------------------------------------------------
 Cut-off   Weathering Tonnage   Grade    Gold   Tonnage     Grade      Gold
 (g/t)        Profile    (Mt)   (g/t)   (Moz)      (Mt)     (g/t)     (Moz)
 --------------------------------------------------------------------------
 0.30           Oxide    34.0    0.67    0.73      25.0      0.59      0.48
 --------------------------------------------------------------------------
 0.35      Transition    11.2    0.84    0.30       5.4      0.88      0.15
 --------------------------------------------------------------------------
 0.50           Fresh    15.7    1.10    0.55      30.3      1.28      1.24
 --------------------------------------------------------------------------
                TOTAL    60.9    0.81    1.59      60.6      0.96      1.87
 --------------------------------------------------------------------------
 (i) Mineral Resources are not mineral reserves and do not have            
  demonstrated economic viability. All figures have been rounded to reflect
  the relative accuracy of the estimates. The cut-off grades are based on a
  gold price of US$1,025 per ounce with CIL processing recoveries of 93%   
  for oxide, 92% for transitional and 78% for fresh material. Indicated and
  Inferred Mineral Resources are all reported within conceptual optimized  
  open pit shells. Unlike 2008, those resource blocks that occur outside   
  the pits shells are not included in this resource estimate. Mt= million  
  metric tonnes. Moz= million troy ounces; g/t= grams gold per tonne.      
 --------------------------------------------------------------------------


Table 2
2008 Audited Mineral Resource Statement(i) for the Bombore deposit, Burkina Faso, West Africa, SRK Consulting, September 20, 2008, Heap Leach Processing Scenario

--------------------------------------------------------------------------
                                        Indicated                Inferred 1
                                 Mineral Resource          Mineral Resource
 --------------------------------------------------------------------------
 Cut-off     Weathering   Tonnage   Grade    Gold   Tonnage   Grade    Gold
 (g/t)          Profile      (Mt)   (g/t)   (Moz)      (Mt)   (g/t)   (Moz)
 --------------------------------------------------------------------------
 0.24             Oxide      30.6    0.53    0.52      32.0    0.46    0.48
 --------------------------------------------------------------------------
 0.25        Transition      13.0    0.56    0.23      15.3    0.50    0.25
 --------------------------------------------------------------------------
 0.52             Fresh       5.7    0.93    0.17      16.8    0.96    0.52
 --------------------------------------------------------------------------
                  TOTAL      49.4    0.59    0.93      64.1    0.61    1.24
 --------------------------------------------------------------------------

    -------------------------------------------------------------------
                 Indicated                                             
                   Mineral                                   Inferred 2
                  Resource                             Mineral Resource
    -------------------------------------------------------------------
    Cut-off     Weathering        Tonnage          Grade           Gold
    (g/t)          Profile           (Mt)          (g/t)          (Moz)
    -------------------------------------------------------------------
    0.24             Oxide            2.3           0.33           0.02
    -------------------------------------------------------------------
    0.25        Transition            5.1           0.34           0.05
    -------------------------------------------------------------------
    0.52             Fresh           20.3           0.71           0.46
    -------------------------------------------------------------------
                     TOTAL           27.7           0.61           0.54
    -------------------------------------------------------------------
(i) Mineral Resources are not mineral reserves and do not have            
demonstrated economic viability. All figures have been rounded to reflect 
the relative accuracy of the estimates. The cut-off grades are based on a 
gold price of US$800 per ounce with heap leach processing recoveries of   
85% for oxide, 81% for transitional and 65% for fresh material. Indicated 
and Inferred 1 Mineral Resources are reported within conceptual optimized 
open pit shells, while Inferred 2 Mineral Resources are all remaining     
resource blocks located outside the pit shell. Mt= million metric tonnes. 
Moz= million troy ounces; g/t= grams gold per tonne                       
--------------------------------------------------------------------------


Several factors account for the difference between the 2010 and 2008 mineral resource estimates as follows:

1.  All 2010 drill samples were subjected to a Leachwell(TM) analysis where
    results higher than 0.2g/t were complemented with a fire assay of the
    leach residue. Many Leachwell(TM) samples from the previous 2008
    estimate did not include leach residue assays for any sample with a
    leach grade below 0.5 g/t. The new expanded LeachWell(TM) residue assay
    database has been used to build a leach model that has been used to
    estimate the grade of the LeachWell(TM) residues for the samples that
    were missing this analysis, based on well defined leach curves for each
    of the major lithological units. The net effect was an increase of about
    4% in the grade as the mineral resource is now more representative of
    the in-situ grade; 
    
2.  The drilling defined several higher grade zones (greater than  0.5 g/t)
    within the large lower grade envelop of the deposit. These zones were
    modeled separately and as a result have contributed significantly to
    higher grades. In the 2008 estimate, only low grade envelopes were used,
    with a top cut of 4 g/t for all of the composited assays. In 2010, the
    composite grades were capped at 1.44, 4.05 and 8.07g/t in the low grade,
    laterite and high grade zones, respectively.  
    
3.  Ordinary kriging was used versus inverse distance squared kriging in the
    2008 estimate. 
    
4.  A higher gold price of US$1,025 was used in this estimate versus US$800
    in 2008. 
    


Drilling on the Bombore property and the mineral resource estimates were supervised by Pascal Marquis, Ph.D., P. Geo., Vice President and Qualified Person for Orezone as defined by National Instrument 43-101 and who has reviewed and approved the technical information in this release. The mineral resource estimates were prepared by Orezone and audited by Dorota El-Rassi, P.Eng. and Glen Cole, P.Geo. of SRK who are Independent Qualified Persons as defined by National Instrument 43-101. Orezone holds a 100% operating interest in the project while the government of Burkina Faso will receive a 3% net smelter royalty and a 10% non-participating (carried) interest should the project go into production.
The Company also announces that Mr. Joseph McCoy has been appointed Chief Financial Officer. Joe holds an MBA and Bachelor of Commerce degree from Concordia University and a project Management diploma from McGill University and brings over 25 years of financial and operational experience to Orezone. Joe replaces Mr. Sean Homuth who has departed to pursue other opportunities. Orezone would like to thank Sean for his dedication and contributions during his tenure.
Orezone is a gold exploration and development company with significant gold resources in Burkina Faso and more than 15 years of operating experience in West Africa, one of the world's fastest growing gold producing regions. Orezone is focused on developing Bombore, the second largest gold deposit in the country and its pipeline of advanced gold projects. Orezone's mission is to create wealth by discovering and developing gold resources in an efficient and responsible manner for the benefit of its shareholders and other stakeholders.
Orezone will hold a conference call Wednesday October 20, 2010 at 11:00hr EST to discuss the Bombore Resource Update. Ron Little and Pascal Marquis will be present for the call. To participate, please call 1-800-403-7802 and log on to https://cc.callinfo.com/r/19ilrrkf56aoa to view the presentation in real-time. The presentation will conclude with a Q&A session.
FORWARD-LOOKING STATEMENTS AND FORWARD-LOOKING INFORMATION: This news release contains certain "forward-looking statements" within the meaning of applicable Canadian securities laws. Forward-looking statements and forward-looking information are frequently characterized by words such as "plan," "expect," "project," "intend," "believe," "anticipate", "estimate" and other similar words, or statements that certain events or conditions "may" or "will" occur.
FORWARD-LOOKING STATEMENTS are based on the opinions and estimates of management at the date the statements are made, and are subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ materially from those projected in the forward-looking statements. These factors include the inherent risks involved in the exploration and development of mineral properties, the uncertainties involved in interpreting drilling results and other geological data, fluctuating metal prices, the possibility of project cost overruns or unanticipated costs and expenses, uncertainties relating to the availability and costs of financing needed in the future and other factors. The Company undertakes no obligation to update forward-looking statements if circumstances or management's estimates or opinions should change. The reader is cautioned not to place undue reliance on forward-looking statements.
Readers are advised that National Instrument 43-101 of the Canadian Securities Administrators requires that each category of mineral reserves and mineral resources be reported separately. Readers should refer to the annual information form of Orezone for the year ended December 31, 2009 and other continuous disclosure documents filed by Orezone since January 1, 2010 available at http://www.sedar.com/, for this detailed information, which is subject to the qualifications and notes set forth therein.

Contacts
Ron Little
Orezone Gold Corporation
CEO
613-241-3699
Toll Free: 888-673-0663
info@orezone.com
Pascal Marquis
Orezone Gold Corporation
V.P. Exploration
613-241-3699
Toll Free: 888-673-0663
pmarquis@orezone.com



More mining stocks info from Investorideas.com and our Gold and Mining Stocks Blog:

Visit Investorideas.com leading mining portals - www.gold-miningstocks.com and www.miningsectorstocks.com to get stock news, directories and showcase mining stocks to follow. Gold and mining investors can research stocks with the mining stocks directory, featuring Gold Stocks, Silver Stocks, Uranium Stocks, Copper Stocks, Zinc Stocks and Precious Metals TSX, TSX Venture, OTC, NASDAQ, AMEX, NYSE, ASX, AIM and other leading Stock Exchanges. The investorideas.com mining stock directory lists over 1100 publicly traded mining stocks for investors. Preview the directory here : http://www.investorideas.com/Gold_Stocks/Stocks_List.asp

 Mining stocks - become a showcase mining stock at www.investorideas.com and see your news and online traction grow immediately for as little as $500 month !